PETITION UNDER SECTION 9 OF THE ARBITRATION AND
CONCILIATION ACT, 1996 FILED BEFORE HON’BLE HIGH
COURT SEEKING URGENT INTERIM ORDERS ON ACCOUNT
OF A DISPUTE ARISING OUT OF A COLLABORATION
AGREEMENT EXECUTED WITH A BUILDER FOR
CONSTRUCTION OF A HIGHWAY RESORT PROJECT ON THE
LAND BELONGING TO THE PETITIONER.
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
INDEX
SNo. Particular Pages
01 Court Fee Sheet
02 Urgent Application
03 Memo of Parties
04 Application under Section 11 of the
Arbitration and Conciliation Act 1996
05 Affidavit in support
06 List of documents alongwith documents
07 Exemption Application with Affidavit in
support
08 Vakalatnama
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
Note – That the petitioner has already filed a Petition under Section 9
of the Arbitration & Conciliation Act 1996 and the same is
pending adjudication before Hon’ble Mr. Justice ______ and
is listed for ______.
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
To
The Deputy Registrar,
________________.
URGENT APPLICATION
Sir,
Will you kindly treat the accompanying petition as urgent one in
accordance with the High Court Rules and Orders.
The ground of urgency are :-
“ Interim Orders have been prayed for ”
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
MEMO OF PARTIES
M/s. _______,
having its Registered office: _______
_______ duly represented through
its Director, _______,
S/o _______, R/o _______
_______ _______ ….Petitioner
Versus
M/s. _______,
having its registered office at : _______
_____________________, through its Director
Mr. _______
Also at
_______
_______,
___________
And also at
M/s. _______,
C/o _______,
_______
_______
…. Respondent
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
APPLICATION FOR EXEMPTION UNDER SECTION 151
C.P.C
Most Respectfully Sheweth :
1. That the petitioner has filed the accompanying petition in this
Hon’ble Court. The contents of the same are not being reproduced here for
the sake of brevity but those may kindly be read as part and parcel of this
application.
2. That the petitioner has filed true/photo copies of documents
alongwith the petition. The certified copies of the same are being applied
and those shall be filed in this Hon’ble Court as soon as they are received
from the Branch.
PRAYER
It is therefore most respectfully prayed that the present petition may
kindly be heard on the strength of true/ photo copies of the documents and
the filing of certified copies may not be insisted upon at this stage, in the
given facts and circumstances of the case in the interest of justice.
Prayed accordingly.
Affidavit is filed in support.
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________ & OTHERS
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENTS
1. Provision under which the Application under Section 9 of the
application is filed Arbitration and Conciliation Act
1996.
2. Name of the applicant with 1. ____________________. duly
address represented through its
Managing Director
__________, having its
Registered Office at
__________, __________
__________
2. Shri __________ S/o Shri
__________ R/O __________,
__________ (__________)
duly represented through his
General Power of Attorney
Holder _______.
(a) Smt. __________ W/O
Shri __________ R/O
__________, __________
(__________) duly
represented through her
General Power of Attorney
Holder __________.
3. Name of the other parties to 1. ____________________,
the Arbitration Agreement __________, __________,
with complete Address __________
2. __________ (Formerly known
as __________)
____________________________
_______________
4. Name and address of Name of Hon’ble Mr. Justice
Arbitrator __________ (Former Judge of
Hon’ble Supreme Court of India)
has been proposed in Legal
Notice dated _____ to be
appointed as Sole Arbitrator in
terms of clause __ of the
Agreement dated _____
05. Name and address of Person Sole Arbitrator to be appointed for
or Institution if any, to adjudication of disputes and the
whom any Function has venue of Arbitration shall be at
been entrusted by the parties __________. (Clause __ of the
to the Arbitration Agreement)
Agreement under
appointment procedure
agreed upon by them.
6. Qualification required if any Dispute are to be referred for
of the Arbitration by the Arbitration by Sole Arbitrator and
agreement of Parties the Arbitration shall be held in
accordance with the Arbitration
and Conciliation Act 1996 and the
venue of Arbitration shall be at
__________, ( Clause __ of the
Agreement ).
7. BRIEF WRITTEN STATEMENT DESCRIBING THE
GENERAL NATURE OF THE DISPUTES AND THE POINTS
AT ISSUES IS GIVEN HEREUNDER
7(1) That the petitioner No 1 is duly represented through its
Managing Director ______. The petitioner No.1 company is primarily
engaged in the business of real estate and has enviable goodwill in the
market.
7(ii) That in the months of _____ Petitioners No.2 and 3
who are husband and wife met _____, Managing Director of the Petitioner
No.1. Petitioner No. 2 represented to _____ that he was the owner of land
admeasuring __ canals __ Marla equivalent to _____ Acres i.e. to say
_____ sq.yds. approx. falling in Khasra No.
_____,_____,_____,______,_____,____ and _____ bearing Khatoni
No._____,_____,_____,______, of the revenue estate of Village ______ in
Controlled Area – 1, __________ which was purchased by him vide Sale
Deed No. ______ dated ______, Sale Deeds No. ______ dated ______,
Sale Deed No. ______ dated ______ and Sale Deed No. ______ dated
______ registered in the office of Sub Registrar, __________
(__________).The Petitioner No. 3 ___ __________ represented that she
was the owner of land admeasuring ______ app. ______ Acre i.e. ______
sq.yds. forming part of Khasra No.______ bearing Khatoni No.______ of
the Revenue Estate of Village ______ in Controlled Area-__, __________,
which was purchased by the Vendor vide Sale Deed No.______ dated
______ registered with the Sub-Registrar, __________. The total land of
petitioners No. 2 and 3 put together was thus ______ sq yds.
7(iii) That the petitioners No. 2 and 3 negotiated with the
petitioner No. 1 company for sale of part of the said land. That in
furtherance thereof, the Petitioner No. 2, out of his total land of ______ sq
yds entered into an Agreement to Sell dated ______ in respect of land
admeasuring ______ i.e. ______ sq yds with the petitioner No. 1, M/s
____________________. The petitioner No. 3 also entered into an
Agreement to Sell dated ______ with petitioner No. 1 company in respect
of the entire land owned by her measuring ______ sq.yds.
7(iv) That the petitioner no 2 further represented to the
petitioner no 1 that from the remaining portion of the land , an area of
______ sq yards could be utilized for the construction of a ______ but he
also at the same time stated that since the permission for change of land use
for construction of a ______ on the said land admeasuring ______ Sq. Yds.
had been granted by the Director Town and Country Planning ______
( __________ ) in his personal name, it was becoming difficult for him to
arrange finances from the bank/ Financial Institutions for the construction
of the ______ as the banks/Financial Institutions generally do not provide
finances to the projects of such large magnitude unless and until the same
was not in the names of Companies / Corporate . The petitioner no 2
represented to the petitioner no 1 that he had already approached the
concerned authorities for changing the name from “ __________ ______ ”
to the name of the company known as “ M/s __________ ______ ” . The
parties further negotiated amongst them and thereafter the petitioner No.2
entered into a collaboration agreement dated ______ with petitioner No. 1
for construction of a ______ on the land measuring ______ Sq.Yds. and it
was agreed that the petitioner No. 1 would provide a built up area of
______ sq.ft. in the proposed ______ to the petitioner No. 2 in
consideration thereof.
7(v) That after the petitioner no 1 and petitioner no 2 had
entered into a Collaboration Agreement dated ______, the petitioner no 2
Shri __________ requested the petitioner No.1 that he was willing to sell
his entitlement of an area of ______ sq.ft. to be provided under the
Collaboration Agreement to the petitioner No.1 for a sum of Rs ______ .
The petitioner no 1 then agreed to buy this area of ______ sq. ft. also, and
accordingly on ______, the petitioner No. 2 entered into an Agreement to
Sell with petitioner No. 2 and the petitioner No.1 bought the area of
______ sq,ft. which was entitlement of petitioner No. 2 under the
Collaboration Agreement dated ______ for a sum of Rs. ______/-.
7(vi) That though the parties had entered into the
Collaboration Agreement dated ______ for the construction of ______ but
the parties felt that since it was a time bound project therefore it would be
appropriate that if they could rope in a company having sound financial
credibility and good reputation in construction projects . It was felt that a
company having sound financials and track record in Highway
Construction Project would be able to complete the construction in a much
faster and efficient manner. Keeping these parameters in mind the
petitioner No. 1 and 2 entered into a Collaboration agreement dated ______
with the respondent company for the construction of ______ and the
petitioner No.3 signed the said Collaboration Agreement as a Confirming
Party. In the said Collaboration Agreement dated ______ the details of all
the transactions iner se between the petitioners i.e. petitioner No.1,
petitioner No.2 and petitioner No.3 were also mentioned for keeping the
record straight and also for clarity. On ______ the petitioners no 2 and 3
also gave respective possessions letters of the land to the petitioner No. 1
company and the petitioner No. 1 company in turn paid the entire
outstanding purchase consideration arising out of all the three Agreements
to Sell dated ______, dated ______ and ______. In other words the
accounts between the petitioners i.e. petitioner No.1, petitioner No.2 &
petitioner No.3 stood settled on ______ in all respects and Receipts for full
and final payments and the possession letters of the lands were duly handed
over by the petitioner No.2 & petitioner No.3 to the petitioner No. 1
company and as such the possession of the land was delivered to the
petitioner No.1 company. Thus the petitioners and more particularly
petitioner No.1 company had got possession of the lands.
It may be pertinent to mention that out of his total lands of ______ sq. yds.,
the petitioner No. 2 __________ retained an area of ___ sq yds for setting
up a Petrol Pump.
BRIEFLY THE SALIENT FEATURES OF THE COLLABORATION
AGREEMENT DATED ______ ARE AS UNDER:-
a. Shri __________ Party of the First Part
b. _____________ Party of the Second Part
c. ____________________ Respondent herein
(Party of the Third Part)
d. Smt. __________ Confirming Party
e. As per Collaboration Agreement dated ______ total land
admeasuring ______ sq yds was to be utilised for construction of a
______. The said land is on the main _______________ Highway
and is situated at the out skirts of __________ City.
f. The party of the first part was entitled to ______ sq.ft. of built up
area in the proposed ______ and the petitioner No. 1 was entitled to
remaining built up and unbuilt up area.
g. Project land as per the Collaboration Agreement included an area of
______ sq.yds (+) ______ sq yds and ______ sq.yds. totaling to
______ sq.yds. which has been provided in the agreement as
“PROJECT LAND”.
h. The respondent who is a Third Party in the said collaboration
agreement was to develop, construct a ______ on the project land.
The respondent was also liable for applying for requisite
license/permission/ sanction from the competent authorities and
obtain necessary sanctions, permissions and approvals.
i. That it was provided in the Collaboration Agreement that the
building plans for construction of ______ were approved by the
Director, Town and Country Planning vide Memo dated ______ and
were valid upto ______ and it was further provided that extension of
time was sought from the Director, Down and Country
Planning,______ (__________) and upon his refusal to provide
further extension, the first party in the Collaboration Agreement
(petitioner No. 2 herein) had approached the Hon’ble High Court of
______ and __________ at ______ and the Hon’ble High Court vide
its order dated ______ had granted the extension for construction of
the ______ project by three years and in pursuance thereof, the
Director Town and Country Planning, __________ vide his Memo
dated ______ had extended the permission for change of land use
for a further period of three years from the date of issue of the said
memo. Thus for all purposes extension granted by the Hon’ble High
Court of ______ & __________ is upto ______ i.e. before ______.
j. Third party i.e. the respondent was to start the development and
construction works within the period of ___ days from the said
collaboration agreement dated ______ at its own costs and expenses
and the ______ was to be completed in a time bound manner i.e.
within the time period stipulated by the statutory authorities.
k. The parties had also agreed that the built up and unbuilt up
areas/space would be sold to prospective customers and all moneys
collected from the bookings/sale/leasing of built up/unbuilt up area
was to be deposited in an Escrow account which was to be opened in
the name of “__________”, The parties had following sharing
arrangement of the amount rendered from every sale/lease of
unbuilt/built-up area/space of the Resort :-
Petitioner No. 1 __% of the amount so rendered
from every sale/lease of
unbuilt/built-up space of the
Resort.
Respondent __% of the amount so rendered
from every sale/lease of
unbuilt/built-up space of the
Resort.
Balance __% of the amount so rendered
from every sale/lease of
unbuilt/built-up space of the
Resort was to be paid by third
party (Respondent) to Mahindru
Charitable Trust and the money
was to be utilised for
charitable/social causes.
7(vii) That as mentioned above the construction of the _____ was to
start within __ days of the execution of the collaboration agreement and it
was surely a time bound project. Timing assumed greater significance
particularly when the plans were valid for only a period of ___ years from
the date of sanction and the construction had to be completed by the
respondent No. 2 on or before ______, The Hon’ble High Court of
______ and ______ at ______ vide it’s order dated ______ had extended
the permission for change of land use by three years only i.e. upto _____.
In this regard it is very pertinent to mention here that the said order dated
______ passed by Hon’ble High Court of ______ & ______ at ______
had given an extension only for a period of three years and therefore the
very purpose of the parties to get into the Collaboration Agreement dated
______ was to get the work executed in a time bound manner, as it was
clear to everyone that if the project is not completed within the stipulated
time period, then the extension of the permissions for change of land use
granted by the Hon’ble High Court would expire on ______ leaving the
petitioners to suffer irreparable and heavy financial losses and also
rendering the said land of no value because after the expiry of the said
period no construction activity can be carried out on the said land and the
land use of the said land would restore back to its original land use i.e. for
agricultural purposes.
7(viii) That after the execution of the Collaboration
Agreement dated _____ the petitioners legitimately expected that the
respondent company would start the development and construction work
within stipulated time period of ___days. The respondent company
however kept on making promises that they were going to commence the
development and construction work at site very shortly, but despite their
promises and assurances no construction actively actually ever started at the
said land. The petitioners reminded them the urgency involved in timely
commencement of construction work but the respondent despite being fully
aware of the repercussions of delays in commencement of construction
activity, did not start the work. Soon it became clear that the respondent
company neither had any intentions nor was in a position to muster
resources to carry out the construction activities within the stipulated time
period.
7(ix) That the petitioners were clearly disappointed
and naturally very agitated because the respondent company had failed to
carry out its contractual obligations. The petitioners also got to know from
various sources that the respondent company perhaps never had adequate
financial and manpower resources to execute the work and the respondent
company had basically entered into a Collaboration Agreement with the
petitioners by misrepresenting the facts.
7(x) That the crucial time was fast running out for
the petitioners to get the construction completed in all respects by ______
and thus serious differences/disputes arose between the parties on account
non-performance of contractual obligations by the respondent company.
Left with no other option, the petitioner No.1 vide legal notice dated
______ terminated the said collaboration agreement and cancelled the same
in all respects and also gave separate Notice for appointment of Arbitrator.
7(xi) That the petitioner No. 2 and also petitioner No. 3 gave their
separate legal notices on similar lines. The Petitioners also gave separate
legal notices to the respondent calling upon the respondent company and its
directors to return the general power of attorneys executed in favour of the
respondent company and also to not to act upon them in any manner.
7(xii) That the petitioners after termination of the said collaboration
agreement did not have any other option but to somehow start and complete
the construction activities either on their own or through any other third
party and that too in a time bound manner so that the entire construction
can take place on or before ______ i.e the said dead line given by the
Hon’ble High Court of Punjab & Haryana at Chandigarh in Civil Writ
Petition No. ______. In furtherance thereof the petitioner company and
other petitioners are making all possible effort to get the construction done
at the site, either on their own or any other third party under a fresh
collaboration agreement as the construction of a Highway Resort is not a
small project and requires huge financial resources and manpower
planning.
Very unfortunately however at this crucial juncture, the respondent
company and some officials claiming to be acting on the instructions of the
directors of the respondent company are threatening to disrupt the
construction activity which the petitioners are proposing to carry out either
through themselves or through any other third party under a fresh
Collaboration Agreement, on the project land. The petitioners are peace
loving and law abiding citizens and they want to complete the construction
on or before ______ so that their interest is not put to jeopardy.
Unfortunately the respondent have malafide intentions and designs and
they want to black mail the petitioners by coercing them to shell out heavy
amounts to them and that is the reason the respondent company and its
Directors and officials are deliberately threatening to disrupt the proposed
construction activity . The respondent perhaps know fully well that if they
succeed in delaying the construction activities then perhaps it would be fate
accompli for the petitioners who then shall suffer irreparable loss and
damages.
7(xiii) That it is respectfully submitted that the petitioners
herein have been wronged by the respondent and they have already suffered
huge financial losses besides loss of goodwill. It may be relevant to
mention here that the petitioners have been left high and dry by the
respondent on account of its failure to carry out its contractual obligations.
It may be noted that if the respondent would have carried out the
construction work and had completed the entire project on time, then the
entire sale proceeds of the Project would have been almost to the tune of
Rs. ___ Crores calculated at the minimum rate of sale price of Rs. _____/-
per sq.ft. multiplied by the total area to be constructed which was ____
sq.ft. app. The petitioner, M/s ______( Petitioner No1 ) who is entitled to
___% of the sale proceeds under the Collaboration Agreement , would then
have received a sum of Rs. ________/- (Rupees ____________ only). The
petitioner No. 1 therefore on account of non-performance of the contractual
obligations by the respondent, clearly stands to lose this amount as per
present calculations, besides a sum of Rs. _____ Crores towards the loss of
goodwill which the petitioner have suffered. Therefore the petitioner No. 1,
even as per present calculations would have a claim of Rs. ______/-
(Rupees thirty-_________ only) against the respondent company and
without prejudice to all other claims that may accrue in favour of petitioner
No. 1 in future, it is submitted that the petitioner No. 1 would have a claim
of minimum of Rs. ______/- (Rupees __________ only) and therefore the
petitioner reserves its right to file a detailed statement of claims before the
learned Arbitrator at an appropriate stage.
7(iv) That as stated hereinabove the petitioner have rightly
terminated the Collaboration Agreement. However disputes and claims if
any, can be referred to the arbitration by a sole arbitrator but respondent
cannot take away the favourable possession of the said land or disrupt the
construction activities scheduled to be carried out by the petitioners.
7(xv) That admittedly there is an arbitration clause in the
Collaboration Agreement and the disputes have to be adjudicate by a sole
arbitrator. The petitioners have already sent their legal notices through
their advocate for appointment of arbitrator and have proposed the name of
Hon’ble Mr. Justice ______ (Former Judge Supreme Court of India) to be
appointed as sole arbitrator for adjudication of the disputes which have
arisen between the parties. The said notices have been duly served on the
respondent. However the respondent company has not replied as yet to the
legal notices tom the petitioners.
7(xvi) That the petitioners have been put in such a situation
where they have hardly any choice but to get the construction done and
make the Highway Project. The petitioners are therefore contemplating to
raise the construction either through their own or through some third party
with whom they can enter into a collaboration agreement. The respondent
on the other hand is nursing malafide intentions to delay the matter and
thus cause wrongful loss to the petitioners. The petitioners respectfully
submit that today the real intention of the respondent company is to some
how make wrongful gains out of their own wrongs. The Respondent
company and its directors namely Shri ______and Shri ______ know very
well that further delay in construction could result in grave financial loss to
the petitioners. Therefore the respondent company and its directors are
now trying to threaten to disrupt the proposed construction by the
petitioners themselves or through any other third party on the said land and
in this process they are trying to coerce the petitioners to cough up huge
sums of money to the respondent who are hell bent of making loss out of
their own wrong/doings. It may be pertinent to mention that the directors of
the respondent company have clearly and very openly threatened the
petitioners that they shall take forcible possession of the land which is
presently with the petitioners and they shall also not allow any one else to
start construction if they are not given Crores of rupees by the petitioners.
The petitioners respectfully submit that it is clear cut case of not only
cheating, fraud but also of black mailing and taking unfair advantage of the
situation by the respondent. The petitioners have genuine apprehension that
the respondent company and its officials will either try to take forceable
possession of the Project Land from the petitioners or else they would
disrupt the proposed/intended construction by the petitioners themselves or
through a third party under a fresh collaboration agreement and therefore
the petitioners have no other efficacious remedy but to approach this
Hon’ble Court for urgent interim orders/protection to protect their legal
rights.
7(xvii)That it is thus a fit case where an urgent interim orders may be
passed in favour of the petitioners and the right of the petitioners be
protected.
7(xviiij) That it is settled preposition of law that in commencement of
any arbitral proceedings is not precondition for exercise of powers by the
Hon’ble High Court under Section 9 of the Act.
8. This Hon’ble Court has the powers to grant interim
relief to protect the interest of the parties.
It has also been held in catena of judgments of the Hon’ble Supreme Court
that Section 9 of the Arbitration and Conciliation Act 1996 only deals with
interim measures by the court and in a fit case where interest of parties
sought to be protected, such interim orders may be passed under section 9
of the Act. It has further been held that a party or a person is entitled to
interim protection if other party is either in the breach of terms of the
agreement or militates against equity, fair play and natural justice. It is
therefore, respectfully submitted that in view of the settled preposition of
law, the Hon’ble Court may be graciously pleased to pass interim Order.
9. That the cause of action to file the present petition
arose on ____ when parties entered into a collaboration agreement
and it arose on all such dates when the respondent company
breached the terms of the collaboration agreement and failed to carry
out their contractual obligations and it further a rose on non-
commencement of construction activities by the respondent
company within the stipulated time period. The cause of action
further arose on ______ when the petitioner No. 1 gave a legal
notice to the respondent and it further arose when the officials/agents
of the respondent threatened the petitioner no. 1 company, its
directors and petitioners 2 and 3 that they would not allow any
construction activity at the site which is in possession of the
petitioners.
CLAIM
10. That the petitioners respectfully submit that on
the present valuation, the petitioner No. 1, M/s ______ would at least have
claim of Rs. ______/- (Rupees ______ only) against the respondent
company and the said claim may also go up in future and therefore without
prejudice to its rights accruing in future, the petitioner would be filing
appropriate statement of claim before the learned Sole Arbitrator who shall
be deciding the disputes between the parties.
ARBITRATION CLAUSE
11. That clause ___ of the Collaboration Agreement
clearly sets out the arbitration clause in respect of Collaboration
Agreement.
COURT FEES
12. The petitioners are paying requisite court fees on this
application.
NON FILING PARA
13. That the petitioners have not filed any other or similar
petitions before this Hon’ble Court or in the Hon’ble Supreme Court of
India.
PRAYER
It is therefore most respectfully prayed that this Hon’ble Court may kindly
be pleased to:-
(a) Restrain the respondent company, its directors namely Shri
______and Shri ______ or their agents/employees or any one acting
for and on their behalf from taking forcible possession of the project
land ( admeasuring ______ sq yards comprising of ______ sq yards
(+) ___sq. yds. and ____ sq. yds. of the petitioners falling in Khasra
No. _____,_____,____,____ bearing Khatoni No.____, ____, _____
and ____ of the revenue estate of Village ____________________,
and further restrain the respondent, its directors/agents/servants or
any one acting for and on behalf of the respondent company from
creating any hindrance or disrupting, disturbing, threatening to
obstruct construction activities by the petitioners themselves or
through a third party under a fresh collaboration agreement to be
carried on the project land comprising _________ sq.yds. situated in
Revenue Estate of Village _________, which is in possession of the
petitioners.
(b) Pass any other or further order(s) as this Hon’ble Court may deem fit
and proper in the given facts and circumstances of the case in the
interest of justice.
Prayed accordingly.
Affidavit is filed in support.
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :