Statement showing the
development works taken-up during
the year 2006-07
(Lake Development)
| Sl.
No |
Name
of Work |
Source
of Finance |
Estimated
Cost |
Date
of Tender |
Tender
Cost |
Name
of the Contractor to whom Tender awarded |
Commencement
Date |
Finish
Date as per Agreement |
Exempted
date of Completion |
Present
stage of work |
photos
of work |
Bills
paid till now |
Bills
submitted and under scrutiny |
Bills
ready payment at scrutiny |
| 1 |
Construction
ceremonial tank at sharanabasaveshwar lake |
Lake
Development |
45.00
lakhs |
27-02-2006 |
45.00
lakhs |
S.Y.Patil |
21-04-06 |
120 days |
- |
under
progress |
|
17,96,403/- |
|
|
| 2 |
Construction
boat jetty platform at sharanabasaveshwar lake |
Lake
Development |
23.00
lakhs |
27-02-2006 |
23.00
lakhs |
Sanjeev
Reddy |
-do- |
120
days |
- |
Near
to completion |
|
1,98,396/- |
|
|
| 3 |
Pedestrian prevent
at Sharanabasaveshwar lake |
Lake
Development |
28.20
lakhs |
27-02-2006 |
28.20
lakhs |
V.
Madhav Das |
-do- |
120
days |
- |
yet to
be start |
|
|
|
|
| 4 |
Grill
fixing at sharanabasaveshwar lake |
Lake
Development |
34.20
lakhs |
27-02-2006 |
34.20
lakhs |
K.L. AC
|
-do- |
120
days |
- |
yet to
be start |
|
|
|
|
Statement showing the
development works taken-up during
the year 2006-07
(I.D.S.M.T)
| Sl.
No |
Name of Work
|
Source
of Finance |
Estimated
Cost |
Date
of Tender |
Tender
Cost |
Name
of the Contractor to whom Tender awarded |
Commencement
Date |
Finish
Date as per Agreement |
Exempted
date of Completion |
Present
stage of work |
photos
of work |
Bills
paid till now |
Bills
submitted and under scrutiny |
Bills
ready payment at scrutiny |
| 1 |
M.S
Angel with chain gate at Mahaboob Gulshan Garden City Corporation,
Gulbarga |
I.D.S.M.T
Scheme |
1.23
Lakhs |
14-09-05 |
1.23
Lakhs |
Md.
Ameer |
- |
30
days |
Except
raining season |
Work
under progress |
- |
- |
- |
- |
| 2 |
Laterite
Stone Path way at Mahaboob Gulshan Garden City Corporation, Gulbarga |
I.D.S.M.T
Scheme |
7.71
Lakhs |
14-09-05 |
7.71
Lakhs |
Mhod.
Sujat Hussain |
- |
60 days |
Except
raining season |
90%
completed |
- |
- |
6,79,705.00 |
- |
| 3 |
Construction
of Compound wall and Grill work to park at Mahaboob Gulshan Garden
City Corporation, Gulbarga |
I.D.S.M.T
Scheme |
18.23
Lakhs |
14-09-05 |
18.23
Lakhs |
P. Anil
Prasad |
- |
90 days |
Except
raining season |
Work under
progress |
- |
- |
- |
- |
| 4 |
Construction
of Compound wall and Grill work Gol Bungalow at Mahaboob Gulshan
Garden City Corporation, Gulbarga |
I.D.S.M.T
Scheme |
2.75
Lakhs |
14-09-05 |
2.75
Lakhs |
Md. Ameer |
- |
- |
completed |
completed |
yes |
2,38,088.00 |
- |
- |
| 5 |
Manufacturing
& errection Tyranasaurus at Mahaboob Gulshan Garden City
Corporation, Gulbarga |
I.D.S.M.T
Scheme |
10.0
Lakhs |
19-11-05 |
10.00
Lakhs |
Chitralaya
Baburao |
- |
9 days |
Except
raining season |
75%
completed |
yes |
- |
- |
- |
|